Ministry of Transportation and Infrastructure – Rossland Arterial Wall

The project included; removal of existing 140 metre long multi-component retaining wall and replacement with a cast-in-place concrete structure; excavation of 1 lane of Hwy 3B/22 and Upper Columbia Road to accommodate removal of stacked rock and bin wall parts; placement of new cast-in-place concrete footing and wall and re-established of both Hwy 3B/22 and Upper Columbia Road.

Project Details
Project:
Highway 3B/22 Rossland Arterial Wall and Road/Utility Improvements
Value:
$2,211,211
Completion:
December 2016
Contact:
Angus Beattie, Ministry Representative
Phone:
(250) 608-1672